Progress of Thermal Power Plant Projects
Index > Information Disclosure > Engineering Information > Progress of Thermal Power Plant Projects
Taichung Combined Cycle Power Plant Project
04/23/24
Project Description
Background
Respond to the growth of domestic power consumption, Taiwan Power Company (TPC) follows the government’s energy policy and promotes the " Taichung Combined Cycle Power Plant Project" to ensure stable power supply. TPC plans to install two gas-fired Combined Cycle units in adjacent to the existing Taichung coal-fired Power Plant station , with a total capacity of about 2.6million kilowatts. This project also includes one berth liquefied natural gas(LNG) unloading pier, a LNG gasification terminal with five LNG storage tanks and associated auxiliary facilities and pipelines, which will be TPC’s first built and self-operated LNG terminal.
Project Location and Scope
The Taichung Combined Cycle Power Plant Project, covering an area of 13.4 hectares, is seated in the Southern of No.9 and No.10 coal-fired units of Taichung Power Plant.
TCPP Project Plant Overall Location
New Design Units Specification
Item |
Parameters |
No. of Unit |
2 |
Single Unit Capacity |
1.3 million kilowatts each |
Unit Type |
two gas-fired Combined Cycle units |
Thermal Efficiency |
64.1% (LHV, Net) |
Net Combustion |
5,616.22 kJ / kWh (LHV, Net) |
Gas turbine |
indoor type, heavy duty for power generation (Heavy Duty), 3,600 r/min |
Steam Turbine |
longitudinal series, condensing, 3,600 r/min |
Heat Recovery Steam Generator |
indoor type, triple pressure reheating |
Generator |
hydrogen or air cooled |
Transformer |
outdoor oil immersion |
Progress Status
Project Progress
Overall progress (%) (March-2024) |
Schedule |
Actual |
Difference |
41.71 |
41.60 |
-0.11 |
Commercial Operation Date (COD)/
Obtaining Electricity Generation License |
Unit 1 |
Unit 2 |
2025/08/31 |
2026/08/31 |
Note:
1. The Project schedule amendment was officially approved by the Executive Yuan on October 5, 2022.
2. Up to 2024/3, Overall progress is delayed about 0.11%. The reasons are due to encountering huge underground obstacles makes it difficult to perform steel sheet pile and point well operations and the poor-quality concrete for the foundation piles is about 4m thick, which causes time-consuming processing and affects the excavation progress.
Construction Status:
-
Power Block:The Bid for Power Block has been awarded on 2020/9/1, the winning tender is GEII(General Electric International Inc)/CTCI consortium team. The construction has started on 2021/9/16, and soil improvement (sand compaction pile method) was completed on 2022/7/21. Foundation Work and plant structure are currently being carried out.
-
Circulating Water System:The Bid opening for Circulating Water System has been awarded on 2020/10/26. The onsite construction work started on 2021/9/1. Foundation Work in Circulating Water Pump House Area completed on 2023/8/26 . At present, the construction of structure in Circulating Water Pump House Area and the first and second elevated internal wall in the pump room area.
Environmental Protection Planning
-
Selective Catalytic Reduction System (SCR) is used for environmental protection.
Pollutant |
Emission Concentration |
SOx |
8 ppm |
NOx |
5 ppm |
TSP |
10 mg/Nm3 |