Δ
TOP
Taiwan Power Company

Progress of Thermal Power Plant Projects

Index > Information Disclosure > Engineering Information > Progress of Thermal Power Plant Projects

Taichung Combined Cycle Power Plant Project

04/23/24

Project Description

Background

Respond to the growth of domestic power consumption, Taiwan Power Company (TPC) follows the government’s energy policy and promotes the " Taichung Combined Cycle Power Plant Project" to ensure stable power supply. TPC plans to install two gas-fired Combined Cycle units in adjacent to the existing Taichung coal-fired Power Plant station , with a total capacity of about 2.6million kilowatts. This project also includes one berth liquefied natural gas(LNG) unloading pier, a LNG gasification terminal with five LNG storage tanks and associated auxiliary facilities and pipelines, which will be TPC’s first built and self-operated LNG terminal.

Project Location and Scope

The Taichung Combined Cycle Power Plant Project, covering an area of 13.4 hectares, is seated in the Southern of No.9 and No.10 coal-fired units of Taichung Power Plant.

TCPP Project Plant Overall Location

 

New Design Units Specification
Item Parameters
No. of Unit 2
Single Unit Capacity 1.3 million kilowatts each
Unit Type two gas-fired Combined Cycle units
Thermal Efficiency 64.1% (LHV, Net)
Net Combustion 5,616.22 kJ / kWh (LHV, Net)
Gas turbine indoor type, heavy duty for power generation (Heavy Duty), 3,600 r/min
Steam Turbine longitudinal series, condensing, 3,600 r/min
Heat Recovery Steam Generator  indoor type, triple pressure reheating
Generator hydrogen or air cooled
Transformer outdoor oil immersion

 

Progress Status

Project Progress
Overall progress (%) (March-2024)
Schedule Actual Difference
41.71 41.60 -0.11
 
Commercial Operation Date (COD)/
Obtaining Electricity Generation License
Unit 1 Unit 2
2025/08/31 2026/08/31
Note:

1. The Project schedule amendment was officially approved by the Executive Yuan on October 5, 2022.

2. Up to 2024/3, Overall progress is delayed about 0.11%. The reasons are due to encountering huge underground obstacles makes it difficult to perform steel sheet pile and point well operations and the poor-quality concrete for the foundation piles is about 4m thick, which causes time-consuming processing and affects the excavation progress.

Construction Status:
  1. Power Block:The Bid for Power Block has been awarded on 2020/9/1, the winning tender is GEII(General Electric International Inc)/CTCI consortium team. The construction has started on 2021/9/16, and soil improvement (sand compaction pile method) was completed on 2022/7/21. Foundation Work and plant structure are currently being carried out.

  2. Circulating Water System:The Bid opening for Circulating Water System has been awarded on 2020/10/26. The onsite construction work started on 2021/9/1. Foundation Work in Circulating Water Pump House Area completed on 2023/8/26 . At present, the construction of structure in Circulating Water Pump House Area and the first and second elevated internal wall in the pump room area.

Environmental Protection Planning

  1. Selective Catalytic Reduction System (SCR) is used for environmental protection.

    Pollutant Emission Concentration
    SOx 8 ppm
    NOx 5 ppm
    TSP 10 mg/Nm3