Progress of Thermal Power Plant Projects
Index > Information Disclosure > Engineering Information > Progress of Thermal Power Plant Projects
Overview of Thermal Power Plants Projects
06/02/21
Taiwan produces very poor energy, and imported energy is as high as 98%. In addition to develop renewable energy, it is still necessary to continue to develop power supplies. Due to the low proportion of base-loaded power supplies in Taiwan, Taipower will adversely control power generation costs and reduce regional power supply and demand. In the unbalanced situation, Taipower actively promoted a number of large-scale power generation projects, including Tung Hsiao, Datan, Hsinta, and Taichung gas recirculation units, which can maintain reasonable spare capacity targets to provide sufficient power support. economic development.
Ongoing Thermal Power Plants Projects
Tunghsiao Power Plant Renewal Project |
Contents of Project |
Construction of three gas combined cycle units, each of which has a capacity of 892.6 MW |
Total investment |
79.557 billion |
Commercial operations date |
Unit 1 2018/02/27 |
Unit 2 2019/05/30 |
Unit 3 2020/05/26 |
Note: 1. The revised schedule of Unit 3 commercial operation is 2020/6/30 as approved. per Executive Yuan's letter No. 1070035115 dated 2018/11/20. The actual date of Unit 3 commercial operation was on 2020/5/26.
Datan Combined Cycle Power Plant Expansion Project |
Contents of Project |
Planning to add three gas combined cycle units, each of which has a capacity of 1 GW at the current plant site, bringing the total capacity to 2.88-3.168GW |
Total investment |
110.46 billion |
Commercial operations date |
Phase two of Unit 7 2024/06/30 |
Unit 8 2022/06/30 |
Unit 9 2023/06/30 |
Hsinta Power Plant Combined Cycle Renewal Project |
Contents of Project |
the total Project capacity is about 3,900 Mega watts of Combined Cycle Units.
(Note 5) |
Total investment |
116.87 billion |
Commercial operations date |
Unit 1 2024/02/29 |
Unit 2 2024/06/30 |
Unit 3 2025/08/31 |
Taichung Combined Cycle Power Plant Project |
Contents of Project |
Planning to add three gas combined cycle units, each of which has a capacity of 1 GW at the current plant site, bringing the total capacity to 2.88-3.168GW |
Total investment |
118.06 billion |
Commercial operations date |
Unit 1 2025/08/31 |
Unit 2 2026/08/31 |
Location of Power Plants