Your browser can not be support! You can still read webpage correctly without script. / Construction Project / Power Construction Projects
| ::: |

裝飾性圖片Power Construction Projects

Power Construction Projects

To cope with future power demand growth, Taipower should supply sufficient power, maintain adequate reserve margins and upgrade power supply safety and stability for people’s livelihoods and the development of business and commerce. Taipower has promoted the following construction projects for generation, transmission and substation, and distribution:

■ Thermal Power Projects

1. Tatan Combined-Cycle Project

The project intends to install two 742.7 MW oil/gas-fired units and four 724.7 MW gas-fired units, with the total capacity of the six units reaching 4,384.2 MW. Combined-Cycle Units 1&2 began commercial operation in August and December 2006. Combined-Cycle Units 3&4 started commercial operation in November 2007. Combined-Cycle Units 5&6 commenced commercial operation in July 2008 and January 2009. The project was completed in 2010.

2. Changgong Thermal Units 1 and 2 Project

The project intends to install two 800 MW supercritical coal-fired units in the Changbin Industrial Park. They are scheduled for commercial operation in January and July 2018. At the end of December 2010, the project was 4.51% complete.

3. Shenao Thermal Power Plant Retrofit Project

This project aims to install two 800 MW supercritical coal-fired units. The existing Shenao Thermal Power Plant will be demolished and the new one will be constructed.

According to the amended project (not yet approved by the government), the investment is estimated at NT$109 billion. Units 1&2 are scheduled for commercial operation in July 2013 and January 2014.

This project will adopt the most advanced technologies to reach the highest generation efficiency and maintain a sound ecological environment. The completion of this project is set to be at the end of 2015. As of the end of December 2011, the project was 2.48% complete.

4. Linkou Thermal Power Plant Retrofit Project

The project aims to install three 800 MW supercritical coal-fired units by the end of 2021. The total investment amount is NT$152.5 billion. Units 1 & 2 are scheduled for commercial operation in July 2015 and July 2016. After Unit 1 is in commercial operation, the existing Units 1 & 2 will be demolished and the installation of Unit 3 will start. It is scheduled for commercial operation in July 2020. As of the end of December 2010, the project was 11.89% complete.

5. Talin Thermal Power Plant Retrofit Project

The project aims to replace low-efficiency power units with four supercritical coal-fired units. With high-efficiency, these units will fulfill the government policies of energy conservation, carbon reduction, pollution reduction, environmental protection, and sufficient power supply. On the assumption that the project passes EIA (Environmental Impact Assessment), the four 800 MW units are scheduled for commercial operation in July 2014, July 2019, and January and July 2020, respectively. The total investment for this project is NT$119.4 billion.

Delayed at the request of the EIA, the installation of the first two units was approved in October 2010. As of the end of 2010, it was 0.8% complete. The revision for commercial operation dates of these two units will be submitted to MOEA for approval in March 2011.

6. Taiwan Power Company Kaohsiung Harbor Coal Unloading Wharf No.107 Project

The Wharf No.107 Project was launched in the northwest side of the Talin Thermal Power Plant to replace the function of the existing Wharf No. 111. This wharf will have the advantages of shortening transport distance and centralizing the management of coal unloading and storage to reduce accidents. The total investment for this project was NT$ 1.23 billion. It was completed on June 30, 2010.

■ Nuclear Power Project

The Fourth Nuclear Power Project

The Fourth Nuclear Power Project utilizes two 1,350 MW Advanced Boiling Water Reactor (ABWR) units supplied by General Electric Company, USA. Foundation excavation for the reactor building started on January 10, 1998. The Atomic Energy Council issued a Construction Permit for the Project in March 1999. The total investment for this project is NT$ 273.6 billion.

The following milestones have been achieved: Unit 1 Reactor Pressure Vessel (RPV) setting (March 20, 2005), Unit 2 RPV setting (October 5, 2006), Unit 1 161KV energized (July 15, 2007), Unit 1 RPV Hydro Test (November 1, 2008), Unit 1 Emergency Core Cooling System Core Injection (April 30, 2010), Flow-Induced Vibration test (September 12, 2010) and Unit 1 345 KV energized (October 28, 2010). The Unit 1 is currently under pre-operation testing.

■ Hydro Power Projects

1. Wanta Expansion and Sunglin Hydro Power Project

● Wanta Expansion Hydro Power Project

In order to fully develop and utilize the water resources between Wushe Dam and Wuchieh Dam, the project aims to build an intake about 300 m upstream from the right bank of the Wushe Dam. The water will run through a 61 m headrace tunnel and a 305 m penstock to the Wanta Hyudro Power Plant downstream. A vertical Francis turbine generation unit (19.7 MW) will be installed in this half-underground powerhouse.

● Sunglin Hydro Power Project

The project aims to construct a weir 400 m upstream from the confluence of Wushe River and Wanta River to collect the tailrace water from the Wanta Hydro Power Plant. The water will run through a 4.7 km headrace tunnel (to the front pond) and a 145 m penstock to the half-underground powerhouse. The tailrace water will then run into the Choshui Creek. Two vertical Francis turbine generation units (18.2 MW and 2.7 MW, totaling 20.9 MW) will be installed.

The Project was started in July 2007 and is scheduled for commercial operation in October 2012. As of the end of 2010, it was 70.46% complete.

2. Tachiachi Hydro Power Plant Chingshan Branch Retrofit Project

Chingshan Hydro Power Plant is Taipower’s largest conventional hydro power plant. The power plant was unable to operate after being damaged by the flood that occurred in July 2, 2005. This led to a reduction of 360 MW in the power system’s fast response spinning reserve and frequency control spinning reserve, which seriously influenced the safety and frequency quality of the power system. The major items of the project include: renovating the underground powerhouse, building a new underground switch yard by using SF6GIS equipment, extending the length of the tailrace tunnel about 2,093 m so that the tailrace water will run into Kukuan Dam for the Kukuan Hydro Power Plant’s power generation, establishing a length of 5,620 m communication tunnel, and replacing major generation equipment. Upon the completion of this project, the net peaking capability of the power system will be 368 MW. This power plant’s annual average power generation of 621.71 million KWh can reduce about 0.269 million tons of CO 2 emissions from gas-fired combined cycle units. This will greatly benefit energy conservation and carbon reduction and power supply stability. The major civil construction for this project was started in July 2010 and will be completed in December 2016. Four units are scheduled for commercial operation in December 2015. As of the end of 2010, the project was 9.47% complete.

■ Wind Power Project

The project is being approved and implemented in 3 phases. 162 wind power units, in total 288.76 MW, will be installed. Of which 144 units have started commercial operation and 18 units are under construction.

● 1. First Phase (January 2003- December 2008)

60 units were installed with a total installed capacity of 98.96 MW at a number of sites, including Shinmen (660 KW x 6), Tatan (I) (1500 KW x 3), Guanyuan (1500 KW x 20), Shianshan (2000 KW x 6), Taichung Harbor (2000 KW x 18), Taichung Power Plant (2000 KW x 4) and Hengchun (1500 KW x 3) Wind Power Stations. All wind turbines in this phase have started commercial operation.

● 2. Second Phase (January 2005~September 2011)

Taipower plans to install 58 units with a total installed capacity of 116 MW at a number of sites: Changgong (2000 KW x 23), Yunlin Miailiao (2000 KW x 15), Sihu (2000 KW x 14), Linko (2000 KW x 3) and Tatan (2000 KW x 3) Wind Power Stations. Except for the Linko and Tatan Wind Power Stations, which are scheduled for commercial operation in early 2011, all the rest have already started commercial operation.

● 3. Third Phase (January 2007~July 2011)

Taipower plans to install 36 units with a total installed capacity of 69 MW at a number of sites: Changgong II (2000 KW x 8), Yunlin Mailiao II (2000 KW x 8), Kinmen Ginsa (2000 KW x 2), Changhwa Wanggong (2300 KW x 10), Tatan II (2300 KW x 2) and Penghu Husi (900 KW x 6) Wind Power Stations. Except for Changhua Wangong and Tatan II Wind Power Stations, which are scheduled for commercial operation in early 2011, all the rest have already started commercial operation.

■ Photovoltaic Project

The first phase of this project was approved and implemented. The total amount of investment on this project is about NT$3.5 billion, with a total generation capacity of 10 MW. The installation sites include Taipower-owned buildings and lands and proper sites provided by outsiders. As of the end of 2010, the bidding for 9 photovoltaic systems was completed, with a total installed capacity of 10,425 KW. Among them, the Taichung Thermal Power Plant 1,500 KW, the Hsinta Thermal Power Plant 950 KW and the Kinmen Culture Park 500 KW were synchronized to the power system in December 2009. It is estimated that the total installed capacity of 10 MW will be reached at the end of 2011. At the end of 2010, the project was 78.28% complete.

| POLICY | SECURITY | COPYRIGHT |
Address:No.242, Sec. 3, Roosevelt Rd., Zhongzheng District, Taipei City 100, Taiwan (R.O.C.) Zip:10016 Tel: 02-23651234

We recommend you to use a monitor with the resolution of 1024*768 pixels to get the best browsing